V model maps the type of test to the stage of development in a project. V model stressed the point that every phase in project should have a test phase also.
Unit Testing
Starting from the bottom the first test level is "Unit Testing". It involves checking that each feature specified in the "Component Design" has been implemented in the component.
In theory, an independent tester should do this, but in practice, the developer usually does it, as they are the only people who understand how a component works. The problem with a component is that it performs only a small part of the functionality of a system, and it relies on co-operating with other parts of the system, which may not have been built yet. To overcome this, the developer either builds, or uses special software to trick the component into believe it is working in a fully functional system. This test maps with the implementation phase and normally developers do the unit testing for the project.
Integration Testing
As the components are constructed and tested they are then linked together to check if they work with each other. It is a fact that two components that have passed all their tests independently, when connected to each other produce one new component full of faults. These tests can be done by specialists, or by the developers.
Integration Testing is not focused on what the components are doing but on how they communicate with each other, as specified in the "System Design". The "System Design" defines relationships between components. The tests are organized to check all the interfaces, until all the components have been built and interfaced to each other producing the whole system. Integration test cases are written when design documents are written.
System Testing
Once the entire system has been built then it has to be tested against the "System Specification" to check if it delivers the features required. It is still developer focused, although specialist developers known as systems testers are normally employed to do it.
In essence, System Testing is not about checking the individual parts of the design, but about checking the system as a whole. In fact, it is one giant component.
System testing can involve a number of specialist types of test to see if all the functional and nonfunctional requirements have been met. In addition to functional requirements, these may include the following types of testing for the non-functional requirements:
Performance - Are the performance criteria met?
Volume - Can large volumes of information be handled?
Stress - Can peak volumes of information be handled?
Documentation - Is the documentation usable for the system?
Robustness - Does the system remain stable under adverse circumstances?
There are many others, the need for which is dictated by how the system is supposed to perform.System test plans are written when the specification of the project is going on.
Acceptance Testing
Acceptance Testing checks the system against the "Requirements". It is similar to systems testing in that the whole system is checked but the important difference is the change in focus:
Systems testing checks that the system that was specified has been delivered. Acceptance Testing checks that the system will deliver what was requested.
The customer should always do acceptance testing and not the developer. The customer knows what is required from the system to achieve value in the business and is the only person qualified to make that judgment. This testing is more of getting the answer for whether is the software delivered as defined by the customer. It is like getting a green flag from the customer that the software is up to the expectation and ready to be used. Acceptance test plans are written during the requirement phase of the project. In real scenario these test plans should be given by the end customer.